Construction Technology Of Under Structure For Raised Access Floors

- Aug 28, 2017 -

1 To install the ground floor of the elevated floors clean, require ground leveling dry. Should be a good cement mortar leveling ground, high and low with a 2 meters horizontal ruler measurement less than 4 mm

2, in the clean and good ground line positioning, to determine the location of each bracket.

3 Install the bracket in the fixed position, install the border and adjust the height of the whole bracket.

4 Bracket Crossbeam assembly, at the same time adjust the level of the beam, the recommended laser level, and then tighten the screws, fixed good beams.

5 Install the movable floor while trimming the movable floor.

6 on the floor after the installation of the foot-kick line to protect and beautify the wall.